Problems with estimation
Regardless of how we put it, one major challenge is that many organizations use estimates as if there was certainty that they can become "correct" - which is a common dysfunction, because it results in undesirable, wasteful behaviours. These could be, for example, as upfront design, padding, "challenging estimates" - and even post-hoc adjustment of the figures to match reality. None of these behaviours help us deliver a better product, and they may even impede quality or time-to-market.
All these aside: we don't know until we tried - that is, there's this thing called "the high probability of low-probability events," so regardless of how much effort we waste on trying to get those activities "right", we could still be wrong due to something we didn't factor.
Category Errors
A common challenge teams face is that not all work is equal: Giving a trivial non-tech example, it doesn't take much expertise to realize that building a tool shack isn't the same category as building a house - and that's not the same category as building a Burj Khalifa.
By simply letting uncategorized work flow into teams, we risk that extremely large packages block the flow of urgent high-value items for a prolonged time. Hence, a first categorization into "Huge, Large, Small" does indeed make sense - The key realization is that these aren't equal.
Hence, dice estimation first categorizes work into the right bin: everything that's workable can be taken up by the team, while everything that isn't workable should be managed appropriately before being worked upon.
Six-sided dice
Story Points worked out terribly, and they led to many dysfunctions - so let's avoid that side track. Instead, let's say that we estimate items in dice values. For small items, our estimation unit would be team-days, for large items, it would be weeks, and for large items, it would be months.
That also leads us to the first logical connection:
One Small Dice at 5 or 6 could already classify for a "1" on a medium dice. We could think about splitting it in two if we want to take it on. On items bigger than 5, we should exercise caution: do we understand it properly, is the cost of implementation warranted - is it really the best thing to do next?
This also applies when an item exceeds 5 on the week count - at that point, it becomes a huge dice: we might want to check a lighweight business case and pivot before proceeding.
How Dice Estimation works
Dice estimation is very easy - you simply ask, "If each day of work was a dice roll, what would be the amount of sides on our dice so that we have enough time to hit a '1' - on average - by the time we are Done?"
That is: if the team expects to be done on 2 days, they would choose 2. If they would expect 3 days, they would choose 3 - if they expect 6, it would be 6 days.
Measuring Confidence
Since dice rolls aren't linear, this form of estimation focuses on levels of confidence in completion within a predefined period of time. Hence, despite the fact that we estimate in days, dice estimation values confidence - and thereby clarity and understanding - above quantity of work.
Estimating with uncertainty
Lightweight estimation
With Dice Estimation, we avoid category errors and institute checkpoints in execution
Of course, you could use dice estimation during Sprint Planning or in a PI-Planning as well, but you don't even need cadences to take advantage of Dice Estimation.
Predictability and Forecasting
As we know, a dice averages at 3.5, so even if we didn't do anything yet except categorizing by dice size, we know that our backlog of workable, small items would take about 2 weeks for 3 items. Once we've done a little bit of work and know how much the completed items took, we can either run a simple Monte Carlo Simulation or apply the Law of Large Numbers to figure out how much known work we have ahead of us. The same applies to the Large and Huge dices, which gives us a fairly decent understanding of when an item might be delivered, based on backlog position.
Not a Performance Metric
Why you should switch from Story Points to Dices
- Sufficient predictability
- Easy plannability
- Execution checkpoints
- Avoiding large batches that block flow
- "Split, Pivot or Defer" decisions
No comments:
Post a Comment